Dams and hydraulic Engineering (Dams and dykes)
- Client: Collectivité Eau du Bassin Rennais (CEBR)
- Assignment: Assistance to the client
- Operator: Local Public Company (SPL) Eau du Bassin Rennais
- Completion date: 2015 – 2019
- Total cost of the assignment: 30 k €
PROJECT DESCRIPTION AND CHARACTERISTICS
Built between 1973 and 1975, with a flooding in 1976, the Chèze dam can store a maximum volume of 14.5 million m³. It is an embankment dam with a tightly sloped inclined core in clay loam materials. It has a maximum height above its foundations of 41 m and length in ridge of 260 m.
ASSIGNMENT
- Monitoring and analysis of auscultation data
- Preparation of an annual report on auscultation
- Advanced Technical Visits
- Full Technical Exam
- Security review