Within the framework of line 15 South, the SADE-Solétanche-Bachy-Solétranche company group Bachy Tunnel is currently producing a test well in Boulogne Billancourt under INGEROP-GEOS work-management.

The purpose of this test pit is to:

  • Strengthen the performance assumptions of the diaphragm walls:

– Two methods: hydraulic and hydroframe;

– Production rate and accuracy of verticality;

– Mechanical strength and deformation;

– Waterproofing;

  • Test a method of building the section through chalk under the groundwater level:

– Opening in the wall;

– Strengthering the ground by injection;

– Retaining structure;

– Measurement of surface deformation;

  • Test the field treatment by Jet Grouting:

– Diameter;

– Resistance;

  • Specify the geotechnical model;

– Stratigraphy;

– Mechanical characteristics;

– Large permeability;

– Presence of flint;