04 50 95 38 14 info@geos-ic.com

South sector town bypass route – Road underpass for railway crossing – Yverdon-Les-Bains – Switzerland

South sector town bypass route – Road underpass for railway crossing – Yverdon-Les-Bains – Switzerland

Civil and structural Engineering

  • Client: Municipality of Yverdon-les-Bains – Department of Works and Environment
  • Assignment: Complete Project Management
  • Total cost of work: 21,500 kCHF (December 2016)
  • Total cost of the assignment: 600 kCHF
  • Completion date: 2014-2019

PROJECT DESCRIPTION AND CHARACTERISTICS

The project consists of designing and constructing a bypass road southwest of the city of Yverdon-les-Bains, aimed at relieving the Yverdon-South junction of the N1 and limiting traffic to the city center.

An access hopper and an underpass with a length of 220m are required for the crossing of the double-track Lausanne-Yverdon railway line.

The characteristics of the project are as follows:

  • Length of the new road about 1 km
  • Mobility track of 3.5 m in own site
  • Bike rack of 1.65 m
  • Width of road 6.70 m
  • Construction of a canal (valley) for the evacuation of surface water run-off
  • Hopper and underpass length 220 m
  • Clearance gauge in the underpass of 5.80 m (height for exceptional convoys)
  • Width of hopper and underpass 14.50 m
  • Depth of underpass 8.5 m below the natural ground
  • Pumping of surface water run-off in the hopper to the evacuation valley
  • Installation of 2 provisional 24 m long steel railway bridges supported on second jet grouted columns (diameter 300mm) for the maintenance of rail traffic throughout the duration of the works
  • Main constraints: poor bearing capacity of the subsoil and a very high groundwater level (70 to 30 cm below the natural ground).
  • 6000 m² of 1m thick slurry walls (permanent supports in access hoppers)
  • 540 m² of sheet piling (provisional supports for groundworks under the railway)
  • 5000 m³ of concrete, 800 tons of reinforcement
  • 20,000 m³ of groundworks for the construction of the crossing structure (hoppers + underpass structures)
  • drain wells for lowering of phreatic groundwater table Inside waterproof site
  • Installation of drainage systems 700 ml

ASSIGNMENT

GEOS is in charge of the project management task as a coordinating contractor for the “Pool GESY” (joint contracting of GEOS and Synaxis SA-Lausanne)

These studies consist in particular of performing the following services (according to SIA 103 (Swiss Standard)):

  • Phase 31: Preliminary project;
  • Phase 32: Construction project;
  • Phase 33: Permit obtaining, procedure/submitted project;
  • Phase 41: Invitations to bid, comparisons of proposals, application for contract awarding;
  • Phase 51: Construction Project;
  • Phase 52: Implementation;
  • Phase 53: Commissioning and completion.

In addition to the basic services, GEOS also conducted the stability analysis of groundworks under the railway and the settlement analysis of provisional railway bridge supports by 3D finite elements modeling on Zsoil software.

Skills

Posted on

2016-08-04